What's the CPWD DSR rate for APP membrane waterproofing?

Torch-applied APP (Atactic Polypropylene) modified bitumen membrane is the most common membrane waterproofing on Indian roofs. CPWD prices it as a complete in-situ multi-course treatment — primer, bonding coats and the membrane itself — per square metre.

Preliminary Using CPWD DSR 2021 (Civil) item rates as published, this worked scenario adds up to ₹454.80 (items 14.87). The item rates are CPWD's Delhi base rates; the quantities and the item mix are NirmanDost's scenario, not a CPWD bundle — adjust both to your site and apply your local cost index.

The recipe

CodeDescriptionUnitRateQtyAmount
14.87 Providing and laying in situ five course water proofing treatment with APP (Atactic Polypropylene) modified Polymeric memberane over roof consisting of first coat of bitumen primer @ 0.40Kg per sqm, 2nd & 4th courses of bonding material @ 1.20 kg/sqm, which shall consist of blown type bitumen of grade 85/25 conforming to IS : 702, 3rd layer of roofing membrane APP modified Polymeric membrane 2.0 mm thick of 3.00 Kg/ sqm weight consisting of five layers prefabricated with centre core as 100 micron HMHDPE film sandwiched on both sides with polymeric mix and the polymeric mix is protected on both side with 20 micron HMHDPE film. 5th, the top most layer shall be finished with brick tiles of class designation 10 grouted with cement mortar 1:3 (1 cement : 3 fine sand) mixed with 2% integral water proofing compound by weight of cement over a 12 mm layer of cement mortar 1:3 (1 cement : 3 fine sand) and finished neat (item of laying brick tiles shall be paid for separately).five-course treatment with 2.0 mm membrane sqm ₹454.80 1 ₹454.80
Total₹454.80

What goes into one unit

Straight from CPWD's own rate analysis for these items — the material and labour they price into the rate above, per one unit of the item. Multiply by your quantity to get a shopping list. Carriage lines are left out: those pay for moving the material, not for extra material.

One sqm of item 14.87 — Providing and laying in situ five course water proofing trea

ItemQtyUnitIn site terms
A.P.P. modified polymeric felt (two layers) 2 mm thick1.1sqm
Bitumen solution primer of approved quality0.4litre
Carriage0.26L.S.
Coal (steam)0.0058quintal
Blown type petroleum bitumen of penetration 85/25 of approved quality0.0024tonne
Beldar0.079day
Painter0.0527day
Mistry0.0043day

Rates and quantities are CPWD's published figures, not a market quotation. Local rates differ — you can override them in the BOQ Builder.

Variations

Seven-course treatment (two membrane layers, 1.5 mm each)

CodeDescriptionUnitRateQtyAmount
14.86 Providing and laying in situ seven course water proofing treatment with APP (Atactic poly-propylene) modified Polymeric memberane over roof consisting of first coat of bitumen primer @ 0.40 Kg per sqm, 2nd, 4th & 6th courses of bonding material @ 1.20 Kg/sqm, which shall consist of blown type bitumen of grade 85/25 conforming to IS : 702, 3rd and 5th layers of roofing membrane APP modified Polymeric membrane 1.5 mm thick of 2.25 Kg/sqm weight consisting of five layers prefabricated with centre core as 20 micron HMHDPE film sandwiched on both sides with polymeric mix and the polymeric mix is protected on both side with 20 micron HMHDPE film. 7th, the top most layer shall be finished with brick tiles of class designation 10 grouted with cement mortar 1:3 (1cement : 3 fine sand) mixed with 2% integral water proofing compound by weight of cement over a 12 mm layer of cement mortar 1:3 (1 cement : 3 fine sand) and finished neat (item of laying brick tiles shall be paid for separately). sqm ₹615 1 ₹615
Total₹615

Notes

  • The top protective brick-tile layer is described in the item but its laying is paid separately — read the description carefully when comparing quotes.
  • For the traditional brick-bat coba treatment see the terrace waterproofing recipe.
  • Rates shown are CPWD Delhi base rates from CPWD DSR 2021 (Civil), as published (our extract of the book is dated 2025) — apply your local market / cost-index variation.
  • CPWD has published later editions since (its site lists DSR 2023); the 2021 figures here are reference rates, not the schedule in force for a current tender.
  • The item mix and quantities on this page are a NirmanDost worked scenario; the rates, units and descriptions in each row are CPWD's, verbatim. Every code opens in CivicMate for the source row.
  • Page last rebuilt 2026-08-17.