NirmanDost

What's the CPWD DSR rate for cement concrete (IPS) flooring?

Plain cement concrete flooring finished with a floating coat of neat cement — what most of India calls IPS flooring. 40 mm thick 1:2:4 is the standard; add a hardener topping for garages and industrial floors.

Preliminary Using CPWD DSR 2021 (Civil) item rates as published, this worked scenario adds up to ₹545 (items 11.3.1). The item rates are CPWD's Delhi base rates; the quantities and the item mix are NirmanDost's scenario, not a CPWD bundle — adjust both to your site and apply your local cost index.

The recipe

CodeDescriptionUnitRateQtyAmount
11.3.1 Cement concrete flooring 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate) finished with a floating coat of neat cement, including cement slurry, but excluding the cost of nosing of steps etc. complete. 40 mm thick with 20 mm nominal size stone aggregate40 mm thick, 20 mm aggregate sqm ₹545 1 ₹545
Total₹545

What goes into one unit

Straight from CPWD's own rate analysis for these items — the material and labour they price into the rate above, per one unit of the item. Multiply by your quantity to get a shopping list. Carriage lines are left out: those pay for moving the material, not for extra material.

One sqm of item 11.3.1 — 40 mm thick with 20 mm nominal size stone aggregate

ItemQtyUnitIn site terms
Stone Aggregate (Single size) : 20 mm nominal size0.0267cum
Coarse sand (zone III) derived from natural sources0.0178cum
Portland Cement (OPC-43 Grade)0.017tonne0.34 bags of 50 kg
Stone Aggregate (Single size) : 10 mm nominal size0.0089cum
Hire charges of Concrete Mixer 0.25 to 0.40 cum with Hopper0.003day
Beldar0.14day
Bhisti0.104day
Mason (brick layer) 2nd class0.08day
Driver (for Road Roller, Concrete Mixer, Truck etc.)0.003day

Rates and quantities are CPWD's published figures, not a market quotation. Local rates differ — you can override them in the BOQ Builder.

Variations

52 mm with concrete hardener topping

CodeDescriptionUnitRateQtyAmount
11.4 52 mm thick cement concrete flooring with concrete hardener topping, under layer 40 mm thick cement concrete 1:2:4 (1 cement : 2 coarse sand : 4 graded stone aggregate 20 mm nominal size) and top layer 12 mm thick cement hardener consisting of mix 1:2 (1 cement hardener mix : 2 graded stone aggregate 6 mm nominal size) by volume, hardening compound mixed @ 2 litre per 50 kg of cement or as per manufacturer's specifications. This includes cost of cement slurry, but excluding the cost of nosing of steps etc. complete. sqm ₹855.90 1 ₹855.90
Total₹855.90

Notes

  • Step nosing is excluded from both items.
  • Rates shown are CPWD Delhi base rates from CPWD DSR 2021 (Civil), as published (our extract of the book is dated 2025) — apply your local market / cost-index variation.
  • CPWD has published later editions since (its site lists DSR 2023); the 2021 figures here are reference rates, not the schedule in force for a current tender.
  • The item mix and quantities on this page are a NirmanDost worked scenario; the rates, units and descriptions in each row are CPWD's, verbatim. Every code opens in CivicMate for the source row.
  • Page last rebuilt 2026-08-17.
Open in the BOQ Builder Browse all DSR rates Get supplier quotes Brand catalogue Ask Nirman AI

Pick up from here