What's the CPWD DSR rate for circuit / submain wiring?
The wiring runs that feed your light and power circuits from the DB — phase + neutral + earth in conduit, priced per metre by conductor size. 2.5 sq.mm is the standard light circuit; 4 and 6 sq.mm feed power circuits and submains.
The recipe
| Code | Description | Unit | Rate | Qty | Amount |
|---|---|---|---|---|---|
| 1.7.2 | Wiring for circuit/ submain wiring along with earth wire with the following sizes of FRLS PVC insulated copper conductor, single core cable in surface/ recessed steel conduit as required — 2 X 2.5 sq. mm + 1 X 2.5 sq. mm earth wire2 x 2.5 sq.mm + 1 x 2.5 sq.mm earth, steel conduit | Metre | ₹369 | 1 | ₹369 |
| Total | ₹369 | ||||
Variations
1.5 sq.mm (light circuit minimum)
| Code | Description | Unit | Rate | Qty | Amount |
|---|---|---|---|---|---|
| 1.7.1 | Wiring for circuit/ submain wiring along with earth wire with the following sizes of FRLS PVC insulated copper conductor, single core cable in surface/ recessed steel conduit as required — 2 X 1.5 sq. mm + 1 X 1.5 sq. mm earth wire | Metre | ₹327 | 1 | ₹327 |
| Total | ₹327 | ||||
4 sq.mm (power circuit)
| Code | Description | Unit | Rate | Qty | Amount |
|---|---|---|---|---|---|
| 1.7.3 | Wiring for circuit/ submain wiring along with earth wire with the following sizes of FRLS PVC insulated copper conductor, single core cable in surface/ recessed steel conduit as required — 2 X 4 sq. mm + 1 X 4 sq. mm earth wire | Metre | ₹428 | 1 | ₹428 |
| Total | ₹428 | ||||
6 sq.mm (submain)
| Code | Description | Unit | Rate | Qty | Amount |
|---|---|---|---|---|---|
| 1.7.4 | Wiring for circuit/ submain wiring along with earth wire with the following sizes of FRLS PVC insulated copper conductor, single core cable in surface/ recessed steel conduit as required — 2 X 6 sq. mm + 1 X 6 sq. mm earth wire | Metre | ₹589 | 1 | ₹589 |
| Total | ₹589 | ||||
Notes
- These per-metre items are how you price the DB-to-circuit backbone; the point wiring items (light point, plug point) then take over from the switch board.
- Rates shown are CPWD Delhi base rates from DSR E&M 2022 (CPWD), edition 2026-06-12 — apply your local market / cost-index variation.