What's the CPWD DSR rate for M20 grade RCC, per cum?

M20 (nominal mix 1:1.5:3) reinforced cement concrete, up to plinth level. Like all CPWD RCC items, this rate is for the CONCRETE ONLY — centering/shuttering and steel reinforcement are separate items (see related recipes).

The recipe

CodeDescriptionUnitRateQtyAmount
5.1.2 Providing and laying in position specified grade of reinforced cement concrete, excluding the cost of centering, shuttering, finishing and reinforcement - All work up to plinth level : 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) derived from natural sources : 3 graded stone aggregate 20 mm nominal size derived from natural sources)nominal mix, up to plinth level cum ₹8,364.20 1 ₹8,364.20
Total₹8,364.20

Variations

Beams & suspended slabs, above plinth up to floor V

CodeDescriptionUnitRateQtyAmount
5.3 Reinforced cement concrete work in beams, suspended floors, roofs having slope up to 15° landings, balconies, shelves, chajjas, lintels, bands, plain window sills, staircases and spiral stair cases above plinth level up to floor five level, excluding the cost of centering, shuttering, finishing and reinforcement, with 1:1.5:3 (1 cement : 1.5 coarse sand (zone-III) : 3 graded stone aggregate 20 mm nominal size). cum ₹10,719.30 1 ₹10,719.30
Total₹10,719.30

Notes

  • Excludes centering, shuttering, finishing and reinforcement — add shuttering-formwork and steel-reinforcement-quintal separately for a complete RCC cost.
  • Rates shown are CPWD Delhi base rates from DSR 2021 (CPWD), edition 2025 — apply your local market / cost-index variation.
  • Generated 2026-07-27.