What's the CPWD DSR rate for centering & shuttering (formwork), per sqm?

Centering and shuttering for RCC work, priced per sqm of contact area and split by structural member — walls, beams, columns and slabs each have their own rate.

The recipe

CodeDescriptionUnitRateQtyAmount
5.9.2 Centering and shuttering including strutting, propping etc. and removal of form for Walls (any thickness) including attached pilasters, butteresses, plinth and string courses etc.walls, any thickness sqm ₹669.55 1 ₹669.55
Total₹669.55

Variations

Beams, lintels & plinth beams

CodeDescriptionUnitRateQtyAmount
5.9.5 Centering and shuttering including strutting, propping etc. and removal of form for Lintels, beams, plinth beams, girders, bressumers and cantilevers sqm ₹608.35 1 ₹608.35
Total₹608.35

Columns, pillars, piers & posts

CodeDescriptionUnitRateQtyAmount
5.9.6 Centering and shuttering including strutting, propping etc. and removal of form for Columns, Pillars, Piers, Abutments, Posts and Struts sqm ₹804.25 1 ₹804.25
Total₹804.25

Suspended floors, roofs & landings

CodeDescriptionUnitRateQtyAmount
5.9.3 Centering and shuttering including strutting, propping etc. and removal of form for Suspended floors, roofs, landings, balconies and access platform sqm ₹766.55 1 ₹766.55
Total₹766.55

Notes

  • Rates shown are CPWD Delhi base rates from DSR 2021 (CPWD), edition 2025 — apply your local market / cost-index variation.