What's the CPWD DSR rate for M25 grade RCC, per cum?
M25 is a design-mix grade in CPWD's book (machine batched, ready-mixed), priced separately from concrete-only work — again excluding shuttering and reinforcement.
The recipe
| Code | Description | Unit | Rate | Qty | Amount |
|---|---|---|---|---|---|
| 5.33.1.1 | Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge. (Note :- Cement content considered in this item is @ 330 kg/cum. Excess/ … All works upto plinth level — Concrete of M25 grade with minimum cement content of 330 kg /cumdesign mix, ready-mixed, up to plinth level | cum | ₹8,683.80 | 1 | ₹8,683.80 |
| Total | ₹8,683.80 | ||||
Variations
Above plinth, up to floor V
| Code | Description | Unit | Rate | Qty | Amount |
|---|---|---|---|---|---|
| 5.33.2.1 | Providing and laying in position machine batched and machine mixed design mix M-25 grade cement concrete for reinforced cement concrete work, using cement content as per approved design mix, including pumping of concrete to site of laying but excluding the cost of centering, shuttering, finishing and reinforcement, including admixtures in recommended proportions as per IS: 9103 to accelerate, retard setting of concrete, improve workability without impairing strength and durability as per direction of Engineer-in-charge. (Note :- Cement content considered in this item is @ 330 kg/cum. Excess/ … All works above plinth level upto floor V level — Concrete of M25 grade with minimum cement content of 330 kg /cum | cum | ₹10,306.20 | 1 | ₹10,306.20 |
| Total | ₹10,306.20 | ||||
Notes
- Excludes centering, shuttering, finishing and reinforcement — add shuttering-formwork and steel-reinforcement-quintal separately for a complete RCC cost.
- Rates shown are CPWD Delhi base rates from DSR 2021 (CPWD), edition 2025 — apply your local market / cost-index variation.
- Generated 2026-07-27.